Construction Projects

Construction Projects


Project Z75 / S.A.P. # 139-124-004
South 4th Street Reconstruction - Elaine Avenue to Country Club Drive
Bid Award Date: April 14th, 2020     -     Prime Contractor: R & G Construction, Marshall, MN
Construction Begin: Week of July 6th, 2020      -     Anticipated Completion: November 2020
Project Details: Reconstruction of South 4th Street including replacement of Sanitary Sewer,
Watermain, Storm Sewer, Grading, Curb and Gutter, Sidewalk, Bike Path, Asphalt Paving and other
miscellaneous work.
Latest Update: October 16th, 2020 - R & G has completed underground utility construction on the
project. The contractor has began placing the first layers of pavement between Country Club Drive and
Southview Drive. Topsoiling and seeding to follow after paving has completed. The contractor has also
began placing curb and gutter between Southview Drive and Elaine Avenue. Pavement will soon follow.
Currently, the intersection of S. 4th St. and Elaine Ave. will be closed to complete construction of the road
section and stay closed until after installation of the concrete gutters. Until construction has completed,
S. 4th Street will be closed to thru traffic.  Only local traffic will be allowed access. Please plan an alternate
route and expect some traffic delays in the area.


Click Here to See Recent Photos

Project Z76
South 1st Street Reconstruction - Southview Drive to north of George Street
Bid Award Date: May 26th, 2020     -     Prime Contractor: Duininck, Inc., Marshall, MN
Construction Begin: September 17th, 2020      -     Anticipated Completion: November 2020
Project Details: Reconstruction of South 1st Street including replacement of Sanitary Sewer,
Watermain, Storm Sewer Catch Basins, Grading, Curb and Gutter, Sidewalk, Asphalt Paving and
other miscellaneous work.
Latest Update: October 16th, 2020 - Duininck has completed underground utility work at the
intersection of S. 1st Street and DeSchepper Street. The contractor has completed watermain and
sanitary sewer main construction between George Street and Southview Drive. Duininck is currently
completing water and sanitary main side street tie-ins, individual water services, and storm sewer
replacement at the intersections. Access to resident homes on S. 1st Street will be limited during
this construction. Please make arrangements for parking vehicles elsewhere, if needed. The roadway
will be closed to all traffic and the contractor is expected to coordinate with residents updates on
excavation activities and when access will be restored, changes for services (garbage, etc.) and any
other items that affect residents. Construction has an anticipated completion in mid-November.
 
Please plan an alternate route and expect some traffic delays in the area.


Click Here to download the Project Flyer

Project Z52 / S.P. # 139-090-005
UCAP Bus Shelters and ADA Improvements - Birch Street, South 4th Street and North 4th Street
Bid Award Date: August 23rd, 2019     -     Prime Contractor: Hisken Construction, Marshall, MN
Construction Begin: May 18th, 2020      -     Completion: July 2nd, 2020
Project Details: Construction of Sidewalk, Curb and Gutter, Bus Stop Shelter Foundations, ADA
Improvements and other miscellaneous work.
Latest Update: July 31st, 2020 - Work on this project has been completed including installation of
the new bus shelters at all three locations.


Click Here to See Recent Photos

Project Z51
2020 Bituminous Overlay and Pedestrian Ramp Improvements Project
Bid Award Date: 
March 24th, 2020     -     Prime Contractor: Duininck, Inc., Marshall, MN
Construction Begin: May 26th, 2020     -     Completion: June 16th, 2020
Project Details: Construction of Asphalt Overlays and Pedestrian Ramp Improvements on city
streets at various locations within the City of Marshall.

Latest Update: July 31st, 2020 - The Contractor has completed the work for this contract.
All ADA pedestrian ramp work has been completed including re-seeding disturbed areas.


Click Here to See Recent Photos

Project Z50
2020 Bituminous Chip Sealing Project
Bid Award Date: March 24th, 2020     -     Prime Contractor: Pearson Bros., Inc., Hanover, MN
Construction Begin: August 17th, 2020     -     Completion: September 14th, 2020
Project Details: Chip sealing on city streets at various locations within the City of Marshall.
Latest Update: September 14th, 2020 - The contractor has completed the work for this contract.

Click Here to download the Project Flyer

Project Z77
Storm Water Pond Improvements
Bid Award Date: June 23rd, 2020     -     Prime Contractor: Towne & Country Excavating LLC, Garvin, MN
Construction Begin: September 14h, 2020     -     Anticipated Completion: October 2020
Project Details: Improvements on the stormwater ponds adjacent to Legion Field Road.
Latest Update: October 16th, 2020 - Towne & Country has completed most of the construction activities
including final grading and seeding in both stormwater ponds. Some minor cleanup items remain to be 
completed.

Click Here to download the Project Flyer

Click Here to See Recent Photos


MERIT Center Pond Outfall Improvements
Bid Award Date: September 8th, 2020     -     Prime Contractor: Towne & Country Excavating LLC, Garvin, MN
Construction Begin: April 2021 (anticipated)     -     Anticipated Completion: July 2021
Project Details: Improvements on the drainage and stormwater pond located at the MERIT
Center Driving Track.

Latest Update: September 14th, 2020 - The City Council has awarded this contract to Towne &
Country Excavating LLC of Garvin, MN. City staff will be discussing project details with the contractor
in the coming weeks.